01Confirm the delay and decision window
Record purchase order, current amendment, product revision, original milestones, missed milestone, report cutoff and last date a decision remains useful. Identify customer, launch, seasonal, storage or booking consequences. Avoid declaring the whole order late when one SKU is delayed but other goods may still create value.
02Establish the physical current state
Reconcile materials received and accepted, work started, conforming units, held units, rejected units, rework, packed units and externally processed quantities by SKU and lot. Support the state with dated records. Remove double counting and do not include unapproved substitutions or unfinished units as available output.
03Verify cause and wider impact
Identify whether the constraint comes from material, equipment, tooling, labor, instructions, quality, approval, subcontractor, packaging, documents or logistics. Distinguish the cause of delay from the reason it was detected late. Open corrective action, supplier change review or quality disposition when those processes are triggered; schedule pressure does not replace them.
04Rebuild the remaining critical path
Map every unfinished operation, queue, transfer, inspection, pack-out and booking dependency. Use actual recent good output, yield, available shifts and resource calendars. Check maintenance, holidays and shared orders. Produce a base forecast and a constrained case, with assumptions visible and the original date preserved for comparison.
05Design safe recovery options
Evaluate SKU resequencing, approved parallel equipment, additional trained labor, reduced changeovers, alternate approved materials or processes, split shipment and route changes. For each option, show quality, evidence, cost, labor, capacity and delivery consequences. Reject options that depend on hidden subcontracting, unauthorized substitution or removal of necessary checks.
06Approve one owned plan
Choose the option through the contract and change process. Name actions, owners, start and finish dates, buyer decisions, added costs, inspection points, document changes and revised cargo-ready date. Define thresholds that trigger immediate escalation, such as material not received, yield below assumption or missed daily good-unit output.
07Monitor execution and close learning
Report actual good units, constraint output, quality holds and milestone variance on the agreed cadence. Reforecast when a threshold is missed rather than moving dates silently. At completion, reconcile quantities, inspections, packing, documents and shipment. Record what planning, visibility or process control will change before the next order.